Work in Progess on the Alstom Facility at Montoir

Begun in January 2013, the construction work on the new Alstom facility, which will specialize in the assembly of offshore wind turbine generators and nacelles, is progressing at Montoir de Bretagne. The buildings are scheduled for delivery in the summer of 2014. Work on producing the first units will start in the autumn, with 100 nacelles eventually to be produced every year.

The work on preparing the platform, which was completed last November, required the installation of 490 construction piles, thereby permitting the elevation of the buildings. The site is in the process of obtaining HEQ (High Environmental Quality) certification. The work is being carried out by Quille Construction in partnership with Colas.